1. 6 workers can build a wall in 24 days. How many days will 2 workers take to build the same wall?
- 72 days
- 86 days
- 58 days
- 54 days
Answer
A. 72 days Work = 6 × 24 = 144 worker-days. 144/2 = 72 days.
2. Nikhil and Fatima together finish a task in 18 days. Nikhil alone takes 30 days. How long will Fatima alone take?
- 45 days
- 41 days
- 54 days
- 36 days
Answer
A. 45 days Fatima's rate = 1/18 − 1/30 = 1/45, so 45 days.
3. Divya alone can do a job in 15 days and Rohit alone in 30 days. They work together for 4 days and then Divya leaves. How many more days will Rohit take to finish?
- 18 days
- 19 days
- 23 days
- 16 days
Answer
A. 18 days In 4 days they finish 4 × (1/15 + 1/30) = 0.4. Remaining 0.6 at 1/30 per day = 18 days.
4. Divya can finish a job in 12 days and Rohit in 4 days. Working together, in how many days will they finish it?
- 1 day
- 3 days
- 2 days
- 4 days
Answer
B. 3 days Work per day = 1/12 + 1/4 = 1/3. Together: 3 days.
5. 4 workers can build a wall in 15 days. How many days will 1 workers take to build the same wall?
- 60 days
- 58 days
- 66 days
- 61 days
Answer
A. 60 days Work = 4 × 15 = 60 worker-days. 60/1 = 60 days.
6. Rohit and Ravi together finish a task in 18 days. Rohit alone takes 30 days. How long will Ravi alone take?
- 54 days
- 43 days
- 45 days
- 36 days
Answer
C. 45 days Ravi's rate = 1/18 − 1/30 = 1/45, so 45 days.
7. Priya alone can do a job in 20 days and Rahul alone in 30 days. They work together for 3 days and then Priya leaves. How many more days will Rahul take to finish?
- 23.5 days
- 16.88 days
- 27 days
- 22.5 days
Answer
D. 22.5 days In 3 days they finish 3 × (1/20 + 1/30) = 0.25. Remaining 0.75 at 1/30 per day = 22.5 days.
8. Rahul can finish a job in 12 days and Meera in 24 days. Working together, in how many days will they finish it?
- 8 days
- 6 days
- 10 days
- 9 days
Answer
A. 8 days Work per day = 1/12 + 1/24 = 1/8. Together: 8 days.
9. 5 workers can build a wall in 22 days. How many days will 1 workers take to build the same wall?
- 121 days
- 110 days
- 132 days
- 112 days
Answer
B. 110 days Work = 5 × 22 = 110 worker-days. 110/1 = 110 days.
10. Ayesha and Meera together finish a task in 18 days. Ayesha alone takes 30 days. How long will Meera alone take?
- 47 days
- 54 days
- 34 days
- 45 days
Answer
D. 45 days Meera's rate = 1/18 − 1/30 = 1/45, so 45 days.
11. Farhan alone can do a job in 15 days and Fatima alone in 30 days. They work together for 2 days and then Farhan leaves. How many more days will Fatima take to finish?
- 24 days
- 23 days
- 25 days
- 26 days
Answer
A. 24 days In 2 days they finish 2 × (1/15 + 1/30) = 0.2. Remaining 0.8 at 1/30 per day = 24 days.
12. Rohit can finish a job in 30 days and Zoya in 20 days. Working together, in how many days will they finish it?
- 14 days
- 9 days
- 15 days
- 12 days
Answer
D. 12 days Work per day = 1/30 + 1/20 = 1/12. Together: 12 days.
13. 18 workers can build a wall in 21 days. How many days will 6 workers take to build the same wall?
- 63 days
- 61 days
- 57 days
- 79 days
Answer
A. 63 days Work = 18 × 21 = 378 worker-days. 378/6 = 63 days.
14. Farhan and Ravi together finish a task in 6 days. Farhan alone takes 10 days. How long will Ravi alone take?
- 13 days
- 15 days
- 19 days
- 12 days
Answer
B. 15 days Ravi's rate = 1/6 − 1/10 = 1/15, so 15 days.
15. Meera alone can do a job in 24 days and Farhan alone in 12 days. They work together for 4 days and then Meera leaves. How many more days will Farhan take to finish?
- 6 days
- 4 days
- 8 days
- 7 days
Answer
A. 6 days In 4 days they finish 4 × (1/24 + 1/12) = 0.5. Remaining 0.5 at 1/12 per day = 6 days.
16. Ayesha can finish a job in 14 days and Nikhil in 35 days. Working together, in how many days will they finish it?
- 13 days
- 8 days
- 9 days
- 10 days
Answer
D. 10 days Work per day = 1/14 + 1/35 = 1/10. Together: 10 days.
17. 8 workers can build a wall in 8 days. How many days will 4 workers take to build the same wall?
- 16 days
- 14 days
- 18 days
- 12 days
Answer
A. 16 days Work = 8 × 8 = 64 worker-days. 64/4 = 16 days.
18. Ravi and Zoya together finish a task in 20 days. Ravi alone takes 30 days. How long will Zoya alone take?
- 54 days
- 60 days
- 66 days
- 62 days
Answer
B. 60 days Zoya's rate = 1/20 − 1/30 = 1/60, so 60 days.
19. Vikram alone can do a job in 20 days and Meera alone in 30 days. They work together for 4 days and then Vikram leaves. How many more days will Meera take to finish?
- 25 days
- 20 days
- 16 days
- 22 days
Answer
B. 20 days In 4 days they finish 4 × (1/20 + 1/30) = 0.33. Remaining 0.67 at 1/30 per day = 20 days.
20. Rohit can finish a job in 8 days and Arjun in 24 days. Working together, in how many days will they finish it?
- 8 days
- 7 days
- 6 days
- 4 days
Answer
C. 6 days Work per day = 1/8 + 1/24 = 1/6. Together: 6 days.
21. 10 workers can build a wall in 13 days. How many days will 5 workers take to build the same wall?
- 23 days
- 26 days
- 31 days
- 21 days
Answer
B. 26 days Work = 10 × 13 = 130 worker-days. 130/5 = 26 days.
22. Kiran and Rohit together finish a task in 12 days. Kiran alone takes 20 days. How long will Rohit alone take?
- 32 days
- 23 days
- 30 days
- 31 days
Answer
C. 30 days Rohit's rate = 1/12 − 1/20 = 1/30, so 30 days.
23. Ravi alone can do a job in 24 days and Fatima alone in 12 days. They work together for 4 days and then Ravi leaves. How many more days will Fatima take to finish?
- 5 days
- 4 days
- 6 days
- 8 days
Answer
C. 6 days In 4 days they finish 4 × (1/24 + 1/12) = 0.5. Remaining 0.5 at 1/12 per day = 6 days.
24. Farhan can finish a job in 20 days and Rahul in 30 days. Working together, in how many days will they finish it?
- 11 days
- 9 days
- 12 days
- 10 days
Answer
C. 12 days Work per day = 1/20 + 1/30 = 1/12. Together: 12 days.
25. 20 workers can build a wall in 28 days. How many days will 4 workers take to build the same wall?
- 126 days
- 140 days
- 141 days
- 154 days
Answer
B. 140 days Work = 20 × 28 = 560 worker-days. 560/4 = 140 days.
26. Ravi and Sana together finish a task in 6 days. Ravi alone takes 10 days. How long will Sana alone take?
- 14 days
- 18 days
- 13 days
- 15 days
Answer
D. 15 days Sana's rate = 1/6 − 1/10 = 1/15, so 15 days.
27. Nikhil alone can do a job in 6 days and Imran alone in 12 days. They work together for 3 days and then Nikhil leaves. How many more days will Imran take to finish?
- 3 days
- 5 days
- 1 day
- 2 days
Answer
A. 3 days In 3 days they finish 3 × (1/6 + 1/12) = 0.75. Remaining 0.25 at 1/12 per day = 3 days.
28. Farhan can finish a job in 21 days and Sana in 42 days. Working together, in how many days will they finish it?
- 12 days
- 11 days
- 16 days
- 14 days
Answer
D. 14 days Work per day = 1/21 + 1/42 = 1/14. Together: 14 days.
29. 9 workers can build a wall in 14 days. How many days will 3 workers take to build the same wall?
- 34 days
- 42 days
- 53 days
- 43 days
Answer
B. 42 days Work = 9 × 14 = 126 worker-days. 126/3 = 42 days.
30. Farhan and Sana together finish a task in 8 days. Farhan alone takes 12 days. How long will Sana alone take?
- 26 days
- 19 days
- 24 days
- 23 days
Answer
C. 24 days Sana's rate = 1/8 − 1/12 = 1/24, so 24 days.
31. Meera alone can do a job in 10 days and Zoya alone in 15 days. They work together for 2 days and then Meera leaves. How many more days will Zoya take to finish?
- 9 days
- 11 days
- 13 days
- 10 days
Answer
D. 10 days In 2 days they finish 2 × (1/10 + 1/15) = 0.33. Remaining 0.67 at 1/15 per day = 10 days.
32. Vikram can finish a job in 18 days and Ravi in 9 days. Working together, in how many days will they finish it?
- 7 days
- 5 days
- 6 days
- 8 days
Answer
C. 6 days Work per day = 1/18 + 1/9 = 1/6. Together: 6 days.
33. 20 workers can build a wall in 17 days. How many days will 5 workers take to build the same wall?
- 68 days
- 51 days
- 67 days
- 70 days
Answer
A. 68 days Work = 20 × 17 = 340 worker-days. 340/5 = 68 days.
34. Vikram and Zoya together finish a task in 15 days. Vikram alone takes 20 days. How long will Zoya alone take?
- 59 days
- 45 days
- 66 days
- 60 days
Answer
D. 60 days Zoya's rate = 1/15 − 1/20 = 1/60, so 60 days.
35. Vikram alone can do a job in 20 days and Priya alone in 30 days. They work together for 3 days and then Vikram leaves. How many more days will Priya take to finish?
- 24.75 days
- 22.5 days
- 24.5 days
- 20.5 days
Answer
B. 22.5 days In 3 days they finish 3 × (1/20 + 1/30) = 0.25. Remaining 0.75 at 1/30 per day = 22.5 days.
36. Sana can finish a job in 18 days and Vikram in 9 days. Working together, in how many days will they finish it?
- 7 days
- 5 days
- 8 days
- 6 days
Answer
D. 6 days Work per day = 1/18 + 1/9 = 1/6. Together: 6 days.
37. 5 workers can build a wall in 20 days. How many days will 1 workers take to build the same wall?
- 125 days
- 90 days
- 100 days
- 120 days
Answer
C. 100 days Work = 5 × 20 = 100 worker-days. 100/1 = 100 days.
38. Imran and Fatima together finish a task in 18 days. Imran alone takes 30 days. How long will Fatima alone take?
- 46 days
- 45 days
- 54 days
- 56 days
Answer
B. 45 days Fatima's rate = 1/18 − 1/30 = 1/45, so 45 days.
39. Farhan alone can do a job in 6 days and Vikram alone in 12 days. They work together for 3 days and then Farhan leaves. How many more days will Vikram take to finish?
- 1 day
- 3 days
- 4 days
- 2 days
Answer
B. 3 days In 3 days they finish 3 × (1/6 + 1/12) = 0.75. Remaining 0.25 at 1/12 per day = 3 days.
40. Sana can finish a job in 6 days and Arjun in 12 days. Working together, in how many days will they finish it?
- 2 days
- 6 days
- 4 days
- 3 days
Answer
C. 4 days Work per day = 1/6 + 1/12 = 1/4. Together: 4 days.
41. Ravi and Rohit together finish a task in 18 days. Ravi alone takes 30 days. How long will Rohit alone take?
- 45 days
- 46 days
- 41 days
- 50 days
Answer
A. 45 days Rohit's rate = 1/18 − 1/30 = 1/45, so 45 days.
42. Arjun alone can do a job in 12 days and Sana alone in 18 days. They work together for 2 days and then Arjun leaves. How many more days will Sana take to finish?
- 15 days
- 13 days
- 10 days
- 16 days
Answer
B. 13 days In 2 days they finish 2 × (1/12 + 1/18) = 0.28. Remaining 0.72 at 1/18 per day = 13 days.
43. Priya can finish a job in 10 days and Nikhil in 15 days. Working together, in how many days will they finish it?
- 6 days
- 7 days
- 5 days
- 4 days
Answer
A. 6 days Work per day = 1/10 + 1/15 = 1/6. Together: 6 days.
44. Priya and Rohit together finish a task in 12 days. Priya alone takes 20 days. How long will Rohit alone take?
- 30 days
- 23 days
- 33 days
- 38 days
Answer
A. 30 days Rohit's rate = 1/12 − 1/20 = 1/30, so 30 days.
45. Rahul alone can do a job in 6 days and Nikhil alone in 12 days. They work together for 2 days and then Rahul leaves. How many more days will Nikhil take to finish?
- 8 days
- 4 days
- 6 days
- 5 days
Answer
C. 6 days In 2 days they finish 2 × (1/6 + 1/12) = 0.5. Remaining 0.5 at 1/12 per day = 6 days.
46. Zoya can finish a job in 40 days and Ayesha in 60 days. Working together, in how many days will they finish it?
- 23 days
- 26 days
- 30 days
- 24 days
Answer
D. 24 days Work per day = 1/40 + 1/60 = 1/24. Together: 24 days.
47. Zoya and Meera together finish a task in 8 days. Zoya alone takes 12 days. How long will Meera alone take?
- 19 days
- 24 days
- 25 days
- 18 days
Answer
B. 24 days Meera's rate = 1/8 − 1/12 = 1/24, so 24 days.
48. Divya alone can do a job in 24 days and Fatima alone in 12 days. They work together for 3 days and then Divya leaves. How many more days will Fatima take to finish?
- 9 days
- 6.75 days
- 6.5 days
- 7.5 days
Answer
D. 7.5 days In 3 days they finish 3 × (1/24 + 1/12) = 0.38. Remaining 0.63 at 1/12 per day = 7.5 days.
49. Fatima and Farhan together finish a task in 8 days. Fatima alone takes 12 days. How long will Farhan alone take?
- 18 days
- 22 days
- 30 days
- 24 days
Answer
D. 24 days Farhan's rate = 1/8 − 1/12 = 1/24, so 24 days.
50. Fatima and Meera together finish a task in 20 days. Fatima alone takes 30 days. How long will Meera alone take?
- 66 days
- 72 days
- 60 days
- 59 days
Answer
C. 60 days Meera's rate = 1/20 − 1/30 = 1/60, so 60 days.
51. A worker completes 92 units of work in 2 days at a constant rate. How many units will they complete in 8 days?
- 367
- 368
- 370
- 361
Answer
B. 368 Daily output = 92/2 = 46; in 8 days = 368.
52. A worker completes 901 units of work in 17 days at a constant rate. How many units will they complete in 5 days?
- 270
- 265
- 263
- 268
Answer
B. 265 Daily output = 901/17 = 53; in 5 days = 265.
53. A worker completes 2340 units of work in 20 days at a constant rate. How many units will they complete in 8 days?
- 937
- 935
- 936
- 931
Answer
C. 936 Daily output = 2340/20 = 117; in 8 days = 936.
54. A worker completes 560 units of work in 8 days at a constant rate. How many units will they complete in 8 days?
- 567
- 557
- 550
- 560
Answer
D. 560 Daily output = 560/8 = 70; in 8 days = 560.
55. A worker completes 1938 units of work in 19 days at a constant rate. How many units will they complete in 6 days?
- 609
- 613
- 612
- 615
Answer
C. 612 Daily output = 1938/19 = 102; in 6 days = 612.
56. A worker completes 315 units of work in 15 days at a constant rate. How many units will they complete in 2 days?
- 35
- 42
- 43
- 37
Answer
B. 42 Daily output = 315/15 = 21; in 2 days = 42.
57. A worker completes 2147 units of work in 19 days at a constant rate. How many units will they complete in 8 days?
- 904
- 909
- 903
- 906
Answer
A. 904 Daily output = 2147/19 = 113; in 8 days = 904.
58. A worker completes 425 units of work in 17 days at a constant rate. How many units will they complete in 2 days?
- 55
- 50
- 52
- 60
Answer
B. 50 Daily output = 425/17 = 25; in 2 days = 50.
59. A worker completes 429 units of work in 11 days at a constant rate. How many units will they complete in 10 days?
- 383
- 387
- 390
- 385
Answer
C. 390 Daily output = 429/11 = 39; in 10 days = 390.
60. A worker completes 2052 units of work in 18 days at a constant rate. How many units will they complete in 14 days?
- 1596
- 1586
- 1597
- 1603
Answer
A. 1596 Daily output = 2052/18 = 114; in 14 days = 1596.
61. A worker completes 585 units of work in 13 days at a constant rate. How many units will they complete in 10 days?
- 445
- 457
- 450
- 452
Answer
C. 450 Daily output = 585/13 = 45; in 10 days = 450.
62. A worker completes 231 units of work in 7 days at a constant rate. How many units will they complete in 4 days?
- 139
- 133
- 132
- 131
Answer
C. 132 Daily output = 231/7 = 33; in 4 days = 132.
63. 10 workers finish a job in 12 days at equal rates. How many days will 6 workers need?
- 20
- 22
- 120
- 70
Answer
A. 20 Total work = 10 × 12 = 120 worker-days; days = 120/6 = 20.